FAB Link Limited has submitted the following applications in December 2016:
- Marine Licence Application for offshore cable laying works to the Marine Management Organisation (MMO) – received December 2017
- Outline Planning Permission Application for a Converter Station to East Devon District Council (EDDC) – received July 2017
- Application for a Certificate of Lawful Development for a proposed use or development in relation to the proposed cable and associated works to East Devon District Council (EDDC) – received June 2017
- FEPA Licence Application for offshore cable laying works to the States of Guernsey (Office of Environmental Health and Pollution Regulation) – waiting decision
FAB Link Limited has submitted the following application in November 2017:
- FEPA Licence Application for offshore cable laying works to the States of Guernsey for an Alternative Offshore Cable Route (Office of Environmental Health and Pollution Regulation)
The applications and accompanying reports and plans, together with the UK cable route environmental risk assessment report are provided below for information.
The public consultation on the draft application file ended on 5th September 2016. FAB Link Limited has taken into consideration comments received from stakeholders and made a number of amendments to the proposals and the reports and plans, as summarised in the Consultation Report, which is also provided below.
1. UK Application File
1.1 Marine Licence Application for offshore cable laying works to the Marine Management Organisation (MMO)
Marine Licence Application Form
Plan of Offshore Cable Route
Offshore Environmental Report
Offshore Environmental Report – Appendices
Draft Marine Archaeology Written Scheme of Investigation
1.2 Outline Planning Permission Application for a Converter Station to East Devon District Council (EDDC)
UK Converter Station Outline Planning Application
Planning Supporting Statement
UK Converter Station Design and Access Statement
Transport Assessment
UK Converter Station Environmental Report
UK Converter Station Environmental Figures
UK Converter Station Environmental Appendices
1.3 Permitted Development for the UK onshore cable laying works
UK Cable Route Application for a Certificate of Lawful Development for a proposed use or development
1.4 Project Information
Project Summary (December 2016)
Consultation Report (December 2016)
Consultation Report (June 2017)